The works diary

A first rebirth.
Twenty-four stages.

Saving the roof, fitting the windows, removing the cement so the brick can finally breathe: the church has had a first rebirth. But the work is far from over: 2027 will be the year of the major fit-out works, to turn this former dump into an unusual gîte.

The main door, during its restoration
24stages told in pictures
6doors
20windows
44openings to close up

24 stages of the works

Preservation

The big clean-up

Doors & windows

Restoring the main door

Doors & windows

Removing the concrete blocks from the windows

Preservation

Chipping cement off the walls

Doors & windows

Sliding doors of the sacristies

Fit-out

Restoring the bell-tower staircase

Roofs & bell tower

Roof of the sacristies

Doors & windows

Restoring the bell-tower window

Garden & orchard

Planting the orchard

Doors & windows

Fitting new joinery

Garden & orchard

Garden upkeep

Roofs & bell tower

Restoring the bell-tower openings

Doors & windows

Restoring the locks

Roofs & bell tower

Roof repair

Doors & windows

Restoring the decorative ironwork

Fit-out

Floorboards on the 2nd floor of the bell tower

Preservation

Lime on the north sacristy wall

Fit-out

Arrival of electricity

Fit-out

First floor of the bell tower

Roofs & bell tower

New opening in the bell tower

Fit-out

Fitting the safety net

Doors & windows

Opening the windows

Preservation

Clearing the rubble

Roofs & bell tower

Repairing the roof

The result

From dump
to gîte.

The road travelled is already huge, but much remains: 2027 will be the year of the major fit-out works, before opening in 2028.